| Location: Clee Hill Quarry, Shropshire. Services Utilised: Project Management, CDM Services, Planning Drawings. | 
| Description: Due to the age and problems with stack emissions a new plant needed to be erected on site. To keep production going the new plant was to be built alongside the existing where the workshop and storage building were located. DPS were engaged to oversee demolition of workshops, civil construction including piling and installation of a 180 tph new asphalt plant made in Denmark. On completion the existing plant was demolished. |
|
| Location: Baston Fen, Cambridgeshire. Services Utilised: Project Management, Site Agent Supervisor. | 
| Description: The existing plant at Baston Fen was old and needed replacing. The client also had a requirement to increase the output capacity. A cleared area was set aside and a new entrance to the road network was constructed. DPS were engaged for total management of the installation including the new services. DPS also acted as Site Agent Supervisor. |
|